Mathematics
B takes 16 days less than A to do a certain piece of work. If both working together can complete the work in 15 days, in how many days will B alone complete the work ?
Linear Equations
3 Likes
Answer
Let A take x days to complete the work so B will take (x - 16) days.
Work done by A alone in 1 day =
Work done by B alone in 1 day =
Work done by A and B together in 1 day is
Given,
If both work together, they finish the work in 15 days.
Value of x will be greater than 16.
∴ x = 40 and x - 16 = 40 - 16 = 24.
Hence, B alone can finish the work in 24 days.
Answered By
2 Likes
Related Questions
Solve (using formula) the equation :
.
By selling an article for ₹ 24, a man gains as much percent as its cost price. Find the cost price of the article.
Divide ₹ 1870 into three parts in such a way that half of the first part, one-third of the second part and one-sixth of the third part are all equal.
If a + c = be and , prove that : a, b, c and d are in proportion.