A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹200 for the first day, ₹250 for the second day, ₹300 for the third day, etc., the penalty for each succeeding day being ₹50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
AP
1 Like
Answer
Since, work has been delayed by 30 days.
Total Penalty (in ₹) : 200 + 250 + 300 + ……… + upto 30 terms
The above sequence is an A.P. with first term (a) = ₹ 200 and common difference = ₹ 50.
By formula,
Sum upto n terms = Sn =
Substituting values we get :
Hence, total penalty = ₹ 27750.
Answered By
1 Like
Related Questions
Find the sum of the first 15 multiples of 8.
Find the sum of the odd numbers between 0 and 50.
A sum of ₹700 is to be used to give seven cash prizes to students of a school for their overall academic performance. If each prize is ₹20 less than its preceding prize, find the value of each of the prizes.
In a school, students thought of planting trees in and around the school to reduce air pollution. It was decided that the number of trees, that each section of each class will plant, will be the same as the class, in which they are studying, e.g., a section of Class I will plant 1 tree, a section of Class II will plant 2 trees and so on till Class XII. There are three sections of each class. How many trees will be planted by the students?